A quote can look perfectly healthy until you check what the percentage actually means. You add 20% to your costs, win the work and assume you‘re keeping a fifth of the sale. You aren’t. That’s a 20% markup, not a 20% margin. The distinction matters for anyone pricing a project, supplying goods or selling a service, but it becomes especially obvious on building jobs where materials and labour add up quickly.

The difference in one £10,000 job

Say a small contractor has £10,000 in direct costs for labour, materials, plant and subcontractors. They add 20% and quote £12,000, excluding VAT. If the work goes exactly to plan, there is £2,000 left after those direct costs.

The markup is 20% because £2,000 is 20% of the £10,000 cost. But the gross margin on that sale is 16.7%, because £2,000 is only one-sixth of the £12,000 selling price. The maths is straightforward once you know which number belongs underneath the percentage.

To achieve a 20% gross margin on the same £10,000 direct cost, the selling price needs to be £12,500, excluding VAT. That is a 25% markup on cost. The two quotes differ by £500 even though someone might casually describe both as ‘adding 20% profit’.

These are worked examples, not typical trade prices or claims about how much builders earn. They also don’t mean the £2,000 is money the owner can take home. Business overheads, other costs and tax still matter.

Why the mistake gets expensive

Imagine that £12,000 quote is agreed, but the job needs another £1,000 of labour and materials that you can’t bill to the customer. Direct costs rise to £11,000. The amount left falls to £1,000, or 8.3% of the unchanged sale price.

That’s why a small difference in the way you price can turn into a big difference in the money left at the end. A missed waste allowance, a return visit, a second skip or an unpriced change to the scope can all eat into that remainder.

The answer isn‘t to choose a huge markup and hope for the best. It’s to identify the real cost of the work, decide what margin you need and make the exclusions and assumptions in the quote clear.

Price the work, not just the materials

The starting point is the cost of actually delivering what you‘ve promised. On a building job that means more than a merchant’s basket and a day rate. Labour should reflect the hours required, including your own time. Add plant or hire, subcontractors, deliveries, disposal and a sensible allowance for foreseeable uncertainty.

Then work out how the job contributes towards your wider overheads: van costs, insurance, software, estimating, admin and the hours you don‘t directly charge a customer for. Whether you include overhead in a job-cost figure or deduct it later, be consistent. Otherwise your ’margin‘ numbers won’t mean the same thing from one quote to another.

Keep contingency separate from the profit you hope to make. A contingency is there for defined delivery risks, not a bonus that should be spent automatically. And if you’re VAT registered, keep the tax treatment consistent with the figures in your estimate rather than treating VAT collected for HMRC as income.

A quick check before you send the quote

First, decide whether your target percentage is a markup on cost or a margin on the selling price. Write that definition on your estimate. If you mean a 20% margin, don’t just multiply cost by 1.2.

Second, make sure you haven’t missed your own labour or counted overhead twice. If your labour figure is already a full customer charge-out rate with overhead and profit built in, adding those allowances again can distort the quote.

Third, put variations in writing. If the customer changes the specification or extra work becomes necessary, agree the price before it becomes another cost you absorb.

Finally, compare the quote with the actual result after the job. What went over budget? Was the extra cost an estimating mistake, changed scope or something you couldn’t reasonably predict? Those answers are more useful than copying the same percentage onto the next quote.

The Builder’s Verdict has a free job price and margin calculator that turns a target margin into an equivalent markup and an ex-VAT selling price using your own labour, materials and overhead inputs. It’s a useful sense check, not a substitute for a properly scoped quote.

One number worth remembering

Markup uses the cost as its starting point. Margin uses the selling price. Before you tell yourself a job makes 20%, check which one you’ve calculated, what costs have been included and how much remains once the job is actually finished.